Supply of Micro TSPUs and Other Telemetry Devices for Collecting and Transmitting Tele-Information from DSRUs

11-Nov-2022. Elsis TS has signed a contract with AB Energijos skirstymo operatoriums (ESO) for supply of Micro TSPUs and other telemetry equipment for the collection and transmission of teleinformation from DSRU.

AB “Energijos skirstymo operatorius” (ESO) is the operator of Lithuania’s electricity and natural gas distribution systems, which distributes electricity and gas and maintains the distribution networks to ensure their reliability and efficiency, troubleshoots network faults and connects new customers.

The contract will provide new Micro TSPU controller kits with power supply, battery packs and communication equipment, mounted in anti-vandal cabinets, for the collection, storage and transmission of telemetry data from the gas pressure regulators in the gas distribution network to the telemetry information system of ESO’s dispatch centre.

The contract, valued at EUR 330 250,00 excluding VAT, will be valid for a period of three years and will be completed on 4 September 2025.

Subcontract for the Installation of a Gas Pressure Limitation Unit at the Marijampolė GDS

11-Nov-2022. Elsis TS has signed a subcontract agreement with Alvora UAB, which has won the tender “Installation of the gas pressure limitation unit at the Marijampolė Gas Distribution Station (hereinafter – GDS)”, announced by Amber Grid AB.

The project will include the installation of a gas pressure limitation unit at the beginning of the main gas pipeline branch to the Marijampolė GDS, as well as the installation of a remote control system (SCADA) that will monitor and control the gas pressure relief unit system.

Elsis TS will carry out the installation, connection and programming of the electrical engineering, earthing and lightning protection, automation and control system, SCADA equipment during the execution of this contract.

The project will modernise the natural gas transmission system of Amber Grid AB using smart technologies and will increase the safety and reliability of the natural gas transmission system for the residents of the municipalities of Vilkaviškis district and Marijampolė.

The works are planned to be completed by 30 June 2023.